Nunavut Housing Corp. distances itself from NCCD partnership
Company was to build up to 2,000 units for Nunavut 3000 under sole-source agreement; Three years in, 114 units are complete with help from subcontractors
Then-premier P.J. Akeeagok, third left from centre, and Lorne Kusugak, centre wearing a checkered shirt, who was Nunavut’s finance minister, stand alongside members of Nunavut Housing Corp., NCC Development Ltd. and students from Nunavut Arctic College in Rankin Inlet in 2022. (File photo by David Lochead)
Once billed as the “biggest business development opportunity” in NCC Development Ltd.’s history, a 10-year agreement for the company to build up to 2,000 housing units in Nunavut by 2030 is stalled.
Instead, Nunavut Housing Corp. is working with construction company NCCD to make sure the initial 316 units NCCD signed on to deliver as part of its first two contracts with the housing corporation are built.
“As a result of the significant delays and logistical issues that have been encountered as part of our agreement with NCCD, no new contracts are being awarded to [the company] for the 2026-27 fiscal year,” said Nathan Carter, spokesperson for Nunavut Housing Corp., Nov. 6 in an email.
NCCD was awarded one contract in 2025 to build two houses in Apex as part of a separate pilot project, Carter said.
Nunavut Housing Corp.’s 10-year partnership with NCC Development was meant to form the backbone of Nunavut 3000, the $2.6-billion Nunavut government initiative to lift the territory out of its housing crisis by building 3,000 housing units between 2022 and 2030.
The idea was that annual negotiated agreements with one company would drive down costs and result in higher quality builds, said Nunavut Housing Corp. in an October 2022 news release announcing the agreement.
NCC Development hailed the Nunavut 3000 partnership in its 2023-24 annual report as a historic milestone and the “biggest business development opportunity” in NCC Development Ltd.’s history.
“While it will be a major test of NCCD capacity, it is a test that NCCD has diligently prepared for over its 28 years of operation,” said the company, which is co-owned by Nunavut’s three regional Inuit associations, in the report.
But after the first two contracts were announced in 2023 and 2024, the builds appeared to stagnate, while contract costs grew in 2025 from $240 million to $270 million.
As of July 2025, a single 18-unit multiplex in Iqaluit was complete. Materials sat in communities for years, including lumber for an eightplex in Naujaat. Those materials were destroyed in a fire in August, almost two years after being delivered to the hamlet.
NCC Development leadership pointed to challenges hiring workers, accessing equipment and gravel, and high shipping costs as major hurdles preventing it from delivering on its commitment.
The company has since subcontracted 12 of its builds to Arctic Fresh Projects Inc. and Birchcliff Development Ltd., Carter said.
As of early November, 114 were complete, and work had not started on 38 units.
“The progress on the [subcontracted projects] is going well, and [NCCD has] committed to come back to us with a plan for those projects that remain under their supervision and have not yet advanced,” said Mathieu Parker, president of Nunavut Housing Corp., in an Oct. 29 update to MLAs in the Committee of the Whole.
Nunatsiaq News requested interviews with Parker and Housing Minister Cecile Nelvana Lyall, but neither were granted as the two leaders were travelling, Carter said. Nunatsiaq News also tried to reach representatives from NCC Development by phone and email, but was unsuccessful.
Nunavut Housing Corp. has since vastly expanded its procurement to 12 contractors, including ABIC Manufacturing (Caivan Group of Companies), Arctic Fresh Projects Inc., Arctic Modular Homes Inc., ArchTech Inc., Birchcliff Development Ltd., Dean’s Utility Services, Eskimo Point Lumber Supply/Airport Service Ltd., Inukshuk Construction Ltd., NL Modular, Nunavut Supplies Inc., Sakku Innovative Building Solutions, and RCM Modular Inc.
When asked for an updated cost for the 316 units that NCC is still working to deliver, Nunavut Housing Corp. declined to say, citing the “number of variables” at play.
“[Nunavut Housing Corp.] looks forward to be able to report on the final cost of these contracts upon project completion,” Carter said in an email.





How some things just remain the same. Inuit get fired at the dim level when a department encounters a problem. Not sure what on earth this Devereau guy has on Premier Main, but he got promoted for this colossal screw up. When is the next election again so we can do a makeover.
They dreamed they could build 200 houses a year for 10 years? There needs to be a serious investigation into this, including the budgets and allocations.
LOL good luck again
At this point, Nunavut 3000 is starting to look more like Nunavut 3000 Excuses. Three years, hundreds of millions of dollars in contracts, 114 homes completed out of 316, and now NHC is quietly distancing itself from what was once celebrated as a groundbreaking partnership. You couldn’t make this stuff up!
Where is the accountability? This isn’t a minor scheduling delay or a few missed sealifts. This is a spectacular failure of project management, procurement oversight and leadership, while Nunavummiut continue to wait for housing.
It’s time to bring the NCC Development board, the NHC board, and the senior leadership of both organizations before the Legislative Assembly for a full public inquiry. And let’s bring former NHC president Eiryn Devereaux back to explain his previous statements to MLAs and Cabinet, reconcile those assurances with what we now know, and answer whether members were misled.
The public deserves to know who approved this arrangement, who monitored it, who knew it was going off the rails, and why nobody appeared to pull the emergency brake.
Apparently, the only thing being constructed on schedule was the list of excuses. Accountability shouldn’t be the only thing in Nunavut with no completion date!
This has the previous Premier’s name all over it, basically why he did not run again in the next election, he would not be Premier or minister again if he even got re-elected which was doubtful.
The first problem was the deputy ministers he appointed, most of them did not know how to do the job including his appointment of Devereau to oversee this housing project.
What I don’t get like many others is why this current Premier would give Devereau a promotion for doing such a terrible job, this makes us not take the GN very seriously and it shows us all what a dysfunctional government we have. With so much money at our government being wasted each year, we do expect better from our government, why is it so difficult?
NHC needs to report publicly how much money was given to NCC and what they got for that money.