It would cost $65M to repair all of Nunavik’s roads and culverts: Assessment
Lidar data used to investigate all 531 kilometres of region’s roads and its 781 culverts
Ahmed Kouki, the Kativik Regional Government’s municipal public works assistant director, left, and James Trimble, the department’s director, present a report to the KRG council in Kuujjuaq Tuesday. (Photo by Dominique Gené)
Repairing all of Nunavik’s roads and culverts could cost an estimated $64.8 million, according to a new report from the Kativik Regional Government’s municipal public works department.
Director James Trimble and assistant director Ahmed Kouki presented the assessment to regional councillors during this week’s Kativik Regional Government council meeting Tuesday in Kuujjuaq.
The compiled data on 531 kilometres of roads and 781 culverts using lidar, which uses laser light for remote sensing. Municipal works staff used the data collected to create a database showing road and culvert conditions across Nunavik and cost estimates for each proposed fix.
The proposals do not include the construction of new roads.
The assessment was carried out under Isurruutiit Program 5, a $153.8-million agreement between the KRG and Quebec’s Municipal Affairs and Housing Ministry to fund infrastructure projects.
Trimble and Kouki presented the assessment’s findings as part of their department’s activity report, which outlined municipal infrastructure projects under the Isurruutiit Program 5.
The public works department is preparing a report on the assessment for the ministry, and the data will also be presented to northern villages in December. Feedback from the villages will help the regional government identify priority projects, said the activity report.
The report does not specify any timeline for work or where the estimated $64.8 million would come from.
Also included in the activity report are updates on several drinking water infrastructure upgrades, reservoir installations, water treatment infrastructure improvements.
In Quaqtaq, for example, upgrades to the pumping station and water treatment plant are more than 50 per cent finished, with completion expected for early December.
In Kangiqsujuaq, wastewater lagoon construction has resumed and is expected to be complete by summer 2027.